Late September Avilla Repairs Hometown News

AVILLA – The East Albion Street portion of the Albion Street Improvement project is nearing completion.  Albion Street between Baum Street and Ley Street may be open as soon as by the end of the day on Friday, September 27.  They plan to have Albion Street open from Main Street to Ley Street before closing Main Street at Albion Street on October 2nd to install the new crosswalks. 

Albion Street will be closed between Main Street and Ley Street from October 8th to the 10th for paving.  Baring delays due to the weather, they plan to have all the work completed on East Albion Street by October 15.

The additional time spent correcting the errors on the engineering design has consumed the time they had allotted for the entire Albion Street Improvements project.  Therefore, work will not immediately begin on West Albion Street.  It may begin late in the Fall if the weather holds out; if not, it will begin in the spring of 2020